On this page Overview Money Timeline Contracts Decisions Outcomes Questions Evidence At a glance
Location Woodstock
Responsible authority Oxford County Current stage Oxford Roads 2/12 intersection reopened; Phase 2A continuesAs of 2026-10-21 Stage and project evidence: [1] [2] [3] [4] [5] [6]
2026 allocation Not established
Next target 2026-11 · Overall completion target The OR2/Dundas–OR12 intersection phase reopened October 21. Phase 2A of the wider reconstruction remains ongoing. The entire project is not complete.
Oxford Road 2 reconstruction from west city limit to Mill Street, with utility and road improvements.
Project 930002
What happens next 2026-11 · Overall completion target
Weather dependent.
Sources for this record: [2]
Who approves and delivers this project? Expenditure approval
Oxford County Council County capital budget authority; individual votes not inferred.
Sources for this record: [1]
Asset owner and delivery lead
Oxford County Public Works County project located within the local municipality; local council is not the County contract manager.
Sources for this record: [7]
Money Reported in-year approvals (1) These amounts use the in-year approvals schedule's basis. They are not substituted for bidder prices, executed contract values, whole-project budgets or payments, or added to other project figures.
Contract Award – within budget $5,495,286 · Report dated 2026-08-12 · Individual approval date not established
Not specified in inspected attachment; no inclusive/exclusive assumption
Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total Individual approval dates are not specified in the row Not specified in inspected attachment; no inclusive/exclusive assumption No supplier assigned from a separate procurement register. Named housing organizations are funding recipients in the project description.
Approval evidence: [6]
Project money
Project cost not published in this record.
Latest spending total not published here.
CAD · Project allocation as published; bid HST basis not established · Approved 2026 new/additional allocation; excludes carryforward unless expressly stated Project money evidence: [1] [2] [3] [4] [5] [6]
Timeline 2026-04-07 Target date passed; milestone status needs a verified update Tentative start Three-phase work
Sources for this record: [2]
2026-07-21 completion Phase 1 reported complete Official County update specifically confirms Phase 1; not whole project.
Sources for this record: [2]
2026-09-14 Target date passed; milestone status needs a verified update Phase 2B expected start Mill/Oxford intersection closure estimated four weeks.
Sources for this record: [2]
2026-10-21 completion Phase 2B intersection complete and reopened The October 21 notice confirms the Oxford Roads 2 and 12 intersection reopened. Phase 2A remains in progress; the whole project is not marked complete.
Sources for this record: [4]
2026-10-21 completion Dundas intersection reopened; wider work continues The OR2/Dundas–OR12 intersection phase reopened October 21. Phase 2A of the wider reconstruction remains ongoing. The entire project is not complete.
Sources for this record: [5]
2026-11 original target Overall completion target Weather dependent.
Sources for this record: [2]
Contracts TENDER-ENG-2026-676 · awardee named in annual register
Network Sewer and Watermain Ltd
Published bid $5,935,704.25
Published award / contract value Not established
Unit price Not established The published bid does not establish the final executed contract value. Not established in annual register
Published bid is not an executed or final contract value. The register provides no dated award or payment history.
Sources for this record: [3]
Open procurement record Decisions 2025-12-10 · Oxford County Council
County approval confirmed by the official budget hub; the detailed approved document is the financial source.
$406,890,915 · Detailed document total of operating plus financed capital; the budget hub headline conflicts.
Consequence: General levy: $96,680,548; library levy: $6,297,357; court security levy: $61,266. Water and wastewater are supported by utility rates.
Sources for this record: [8] [9]
2026-08-12 · FS2026-17 Attachment 2
Contract Award – within budget
$5,495,286 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total
Consequence: OR2 Dundas reconstruction CPKC overhead railway to OR12 Mill Street
Sources for this record: [6]
Outcomes Completion not confirmed.
Questions What is the current approved project total, including carryforward and changes? What spending and final completion or acceptance records are available? Scope & interpretation notes Shared 930002 allocation $4.3m also covers Thamesford lane reconfiguration. Amount not assigned in full to this project; separate water/storm costs also apply. Sources & evidence These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: county-budget2026-p122
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 122; printed page 122
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library
Source ID: county-construction
Publisher Oxford County
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status official project notice
Passage / page Named project sections; updates through September 2026 Open in source library
Source ID: county-award-tender-eng-2026-676
Publisher Oxford County
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status register entry
Passage / page TENDER-ENG-2026-676
Evidence notes Full annual register downloaded and parsed. Contract-value field is -- for this entry; this is not proof the contract does not exist. Open in source library
Source ID: county-construction-dundas-20261021
Publisher Oxford County
Source date 2026-10-21
Published 2026-10-21
Reporting period 2026
Reviewed 2026-10-29
Retrieved 2026-10-29
Verified 2026-10-29
Evidence status verified_primary
Decision / approval status official source
Passage / page Oxford Road 2/Dundas Street reconstruction: October 21 update
Evidence notes Phase 2B at the Oxford Roads 2 and 12 intersection is complete and the intersection reopened. Phase 2A continues; this is not whole-project completion. Open in source library
Source ID: oct30-or2
Source date 2026-10-21
Event / reporting date 2026-10-21
Reviewed 2026-10-30
Retrieved 2026-10-30
Evidence status verified_primary
Decision / approval status partially complete
Evidence note Primary-source body reviewed in the October 30 audit The entire project is not complete. Open in source library
Source ID: oct30-county-inyear-approvals
Source date 2026-08-12
Date context Report dated August 12, 2026; publication and individual approval dates not established
Event / reporting date 2026-08-12
Reviewed 2026-10-30
Retrieved 2026-10-30
Evidence status verified_primary
Evidence note 15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified. Open in source library
Source ID: county-budget2026-p5
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 5; printed page 5
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library
Source ID: county-budget-hub
Publisher Oxford County
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status official approval summary
Passage / page 2026 approved budget section
Evidence notes The hub reports $406.1 million total and $278.2 million operating, while the approved detailed PDF reports $406,890,915 and $279,035,275. Open in source library
Source ID: county-budget2026-p58
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 58; printed page 58
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library
Copy this view Print