02Follow the moneyWoodstock

Woodstock · Procurement record

808 Dundas architectural design services

PW 2026-19

Money & projects Explore sections
Oxford County procurementstaff recommendation; Council disposition not extracted

Supplier

Not established in the reviewed record

Procurement method
proposed single-source
Award date
Not established
Contract term
Not established

From bid to payment

staff recommendation; Council disposition not extracted

  1. Published bidAmount not published
  2. Recommendation$250,000JPM Architecture Inc.
  3. Award / contractAmount not published
  4. Recorded paymentsAmount not publishedNo payment amounts attached
Not specified in opened official preview · Bid, award and payment are separate measures.

Recommended ceiling is up to $250,000; no signed-contract, award or payment conclusion.

Recommendation awaiting a verified decision

JPM Architecture Inc. · $250,000

A staff recommendation does not establish a Council award or an executed contract.

Contract changes & payments

Contract changes unconfirmed.

Payments not confirmed.

Related project

County · Housing & community services

808 Dundas: from purchase to an operating support centre

The June 1 announcement describes a 55-bed centre at 808 Dundas Street expected to open in spring 2028. The purchase closed May 29, 2026. Later design, tendering and renovation milestones were estimates, not proof of completion. June announcement reread, not new October progress. Do not route someone needing shelter today to this planned facility.

Woodstock · 808 Dundas Street, Woodstock

Property acquired; spring 2028 opening remains a target
2026 allocation
Not established
Next target
2028-04 · Centre opening target
Latest update
2026-09-21 · Engagement feedback published

What still needs an answer

  • What did Council resolve on the proposed design contract, and what is its executed value?

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. May 27 Council preview — 808 Dundas design services

    Source ID: county-v7-jpm-design-proposal

    Publisher
    Oxford County
    Published
    2026-05-25
    Event / reporting date
    2026-05-25
    Reporting period
    2026
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Decision / approval status
    staff recommendation described in official agenda preview
    Passage / page
    Contract award for renovation work; PW 2026-19
    Evidence notes
    Council minutes link is in manifest, but minutes attachment could not be opened. The article says Council is being asked to approve; no award inferred.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

Open the full money explanation