The June 1 announcement describes a 55-bed centre at 808 Dundas Street expected to open in spring 2028. The purchase closed May 29, 2026. Later design, tendering and renovation milestones were estimates, not proof of completion. June announcement reread, not new October progress. Do not route someone needing shelter today to this planned facility.
Planned 55-bed, continuously staffed homelessness support centre with support services; separate from the HART Hub.
Who approves and delivers this project?
Owner and homelessness service lead
Oxford County
Responsible for acquisition, renovation procurement and the service-delivery arrangements.
A recurring annual estimate, separate from capital.
Latest spending total not published here.
CAD · Tax treatment not specified in release · Forecast is approximate total capital cost, including the $4.55 million acquisition and $3.25 million renovation, legal and administrative costs. Estimated $2.4 million annual operation is separate.
Woodstock Homelessness Support Centre remains a planned facility
The June 1 announcement describes a 55-bed centre at 808 Dundas Street expected to open in spring 2028. The purchase closed May 29, 2026. Later design, tendering and renovation milestones were estimates, not proof of completion. June announcement reread, not new October progress. Do not route someone needing shelter today to this planned facility.
The $4.55 million acquisition price is confirmed, but no full-project actual expenditure series has been extracted. The capital estimate and annual operating estimate must not be added into a single project total.
Sources & evidence
These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
official project update; September 23 Council disposition not extracted
Passage / page
September 21 update and July 17 public meeting update
Evidence notes
Opened complete public project page. September update identifies tendering as next step and retains spring 2028 opening target. Do not label tendering complete or infer a revised opening date; spring 2028 was already in the June announcement.
staff recommendation described in official agenda preview
Passage / page
Contract award for renovation work; PW 2026-19
Evidence notes
Council minutes link is in manifest, but minutes attachment could not be opened. The article says Council is being asked to approve; no award inferred.
Spring 2028 forecast; exact opening not established
Published
2026-06-01
Event / reporting date
2028-04
Reviewed
2026-10-30
Retrieved
2026-10-30
Evidence status
verified_primary
Decision / approval status
planned; not an operating service
Evidence note
Primary-source body reviewed in the October 30 audit June announcement reread, not new October progress. Do not route someone needing shelter today to this planned facility. Spring 2028 forecast; exact opening not established